Meter only

Meter installations. Managed for you.

If the DNO (definition available) or Gas Transporter has finished the infrastructure — or you already have a live MPAN (definition available)/MPRN (definition available) that needs swapping or upgrading — this is the short path. Many jobs completed within 10 working days.

Typical timescale
5–20 working days

From signed supply contract to meter installed and energised. Most jobs completed within 10 working days.

Best case
5 working days
Plan around
15 working days
Need it sooner?
Ask about urgent meter installations
Most installs

£0 to pay for the meter installation.

In the majority of cases the cost of the meter installation is covered by the energy supplier or built directly into your supply contract — meaning nothing for you to pay out of pocket on the install itself.

Stage by stage

A short, predictable path.

Five steps from signed quote to live meter. Most customers only have to act on steps 1, 2 and 4 — we do the rest in the background.

  1. 1
    Step 1
    Day 1–2

    Confirm the supply position

    We collect your MPAN (definition available)/MPRN (definition available) (or DNO (definition available)/GT (definition available) completion paperwork), check the metering profile and confirm load and capacity.

    YouSend the MPAN (definition available)/MPRN (definition available) and a photo of the meter position.
  2. 2
    Step 2
    Day 2–5

    Supply contract

    We tender across our 30+ supplier panel — matrix or bespoke pricing — and get the supply contract signed and accepted.

    YouReview the contract pack and e-sign.
  3. 3
    Step 3
    Day 5–8

    Registration & MOP (definition available) appointment

    We arrange to register the supply and appoint the Meter Operator and Data Collector.

    YouNothing — we handle the registrations.
  4. 4
    Step 4
    Day 8–15

    Meter install booked

    The MOP (definition available) contacts you to book a slot. We check the site is ready and the meter position is safe and accessible.

    YouConfirm a slot and make sure the meter position is clear.
  5. 5
    Step 5
    Day 10–20

    Energisation & live data

    Meter installed, supply on, billing data flowing. Your account manager handles any post-install snags.

    YouSwitch on and start using your supply.

Send your MPAN (definition available) or MPRN (definition available) and we'll book it.

Three minutes to start a quote. We'll come back with a meter date.

Start my meter quote